Wet weather has delayed the building about 1 week, but we are still planning to finish in June.   Work is now mainly on the internals of the building so weather delays should be minimal.  At this time, our attention is focused on working with the NSW Department of Health for special certifications and working on major equipment purchases.  Both these have a long lead time, but we are still planning finalizing all by late this year or early next year.   Again all this is subject to any unexpected events or delaying effects related to the corona virus.